Previously, the Load Center did not comply with the power factor requirement indicated in the Grid Code.
Therefore, an equipment was implemented, which could adapt to the reactive power demand by reading two feeders at different voltages and perform a dynamic compensation to ensure compliance at the PCC (114 kV).
STATCOM 5 MVAR @ 34.5 kV, Wye Connection
General
Engineers involved in this case study
Eng. Eulalio Rodríguez / Eng. Alberto González / Eng. Santiago Esparza